हिमाचल प्रदेश विद्युत नियामक आयोग

Himachal Pradesh Electricity Regulatory Commission

Public Notice Inviting Suggestions/ Objections w.r.t. Petition No. 139/2026 for the approval of Capital cost and determination of tariff for the 5th Control Period from CoD to FY2028-29 for 220/132/33kV (220/132kV, 160/200MVA + 132/33kV, 2×25/31.5MVA) AIS Sub-station at Kala Amb (Asset-1), 220 kV Transmission Line on Multi Circuit Towers from 400/220 kV PGCIL Pooling Sub-station at Kala Amb to 220/132 kV HPPTCL Sub-station at Kala Amb (Asset-2) and Construction of 132 kV M/C Transmission line on 220kV M/C towers with ACSR ‘Zebra’ conductor from 220/132/33 kV Kala Amb (HPPTCL) to Tower No.19 of 132kV Jamta- Kala Amb (Johron) Transmission Line along with stringing & sagging of ACSR Panther Conductor on 2nd Circuit of 132 kV Jamta – Kala Amb line on 132 kV D/C Towers from T-1 (Devani) to T-14 (Kala Amb) (Asset-3)