हिमाचल प्रदेश विद्युत नियामक आयोग

Himachal Pradesh Electricity Regulatory Commission

Before Hon’ble HPERC in the Matter of Approval of Capital Cost and determination of Tariff for the period from COD (20.05.2022) to FY 2023-24 for 66kV GIS Switching Sub-station at Urni (Asset-1) and for the period from COD (20.05.2022) to FY 2023-24 for 66kV D/C Line from Urni Switching Station to Wangtoo Sub-station (Asset-2) of HPPTCL