Generation

Keyword Sat, Apr 27th, 2024
Sr.No. Description Date Of Order
1
Before Hon'ble HPERC in the Matter of Approval and Inclusion of Capital Expenditure Schemes for Restoration of 3x42 MW Larji Power House in the CAPEX Plan of Generation Business of HPSEBL for 4th MYT Control Period (FY20 to FY24)14-03-2024
2
Before Hon'ble HPERC in the Matter of True-up for third MYT Control Period (FY 2014-15 to FY 2018-19) & Mid-Term Performance Review for Fourth MYT Control Period (FY 2019-20 to FY 2023-24) for Generation Business26-02-2024
3
Before Hon'ble HPERC in the Matter of True-Up of tariff for FY 2019-20 to FY 2021-22 and Mid Term Review for FY 2022-23 and FY 2023-24 for sale of power from Baspa II HEP to HPSEBL16-05-2023
4
Order on determination of Capital Cost and Project Specific Levelized Tariff for Ghanvi II SHEP (10 MW)28-09-2022
5
Before the Himachal Pradesh Electricity Regulatory Commission in the matter of Petition for ARR for fourth MYT Control Period (FY2019-20 to FY 2023-24) and True-up for second MYT Control Period (FY 2011-12 to FY 2013-14) for Generation Business of HPSEB Ltd.11-11-2021
6
True Up Order for BASPA II HEP for FY 2017-18 to FY 2018-1907-07-2020
7
Multi-Year Tariff Order for BASPA II HEP for FY 2019-20 to FY 2023-2429-06-2019
8
True Up Order for baspa-II HEP for FY12-14.30-03-2015
9
Multi Year Tariff For HPSEBL for Generarion Business For the Period FY-14-15 to 2018-19.10-06-2014
10
Multi Year Tariff For Baspa-II HEP For FY2014-15 to 2018-19.06-06-2014
11
Multi Year Tariff For Baspa-II for FY 12 to FY 1415-07-2011
12
Order for Determination of Capital Cost of Larji HEP (126 MW) and other related issues07-07-2011
13
Determination of Multi year Tariff for Baspa II HEP For FY 2009-1130-03-2009
14
True Up Order For Tariff Order of FY 2006-2007.29-04-2008